Operational Readiness and Airport Transfer (ORAT) for [the Greenfield] Incheon-Seoul International Airport


Project Synopsis

Provision of management support to Incheon International Airport Corporation (IIAC) and project team to fulfil the implementation of the Operational Readiness & Airport Transfer (ORAT) programme at the new Incheon-Seoul International Airport10.

Tasks included support towards:

  • Establishment of the project’s bidding, concept and programme development;
  • ORAT backstopping provisions;
  • Contract management.

10. Tasks were performed via Deutsche AeroConsult GmbH, a 100% subsidiary of Frankfurt Main International Airport through the participation of Azlan Morad, and within his scope of responsibility as Associate Director at the material time.

Operational Readiness and Airport Transfer (ORAT) for [the Greenfield] Incheon-Seoul International Airport